|
Phases and Timeline |
|
In response to the
competition requirement that the new Capitol be built in a
fiscally responsible manner, Bertram Goodhue's "cross within
square" floor plan allowed construction to begin around the
old Capitol while still occupied, and workers still
conducting state business. After the north and south
sections of the outer square of the new building were
constructed around the old, the offices were moved into the
new and the old demolished. The second construction phase
included the east side of the square and the north, south
and east arms of the cross. Third phase construction
completed the tower. In the final phase, workers finished
the remaining west arm of the cross, completing the building
in 1932 after ten years of construction. When landscaping
was completed in 1934, the Capitol was fully paid for at a
cost of $9.8 million. |
|
|
Timeline of Capitol
Commission and Construction Activitiy: |
||
|
|
February, 1919 |
|
Legislature passed Bill to create Capitol Commission and fund Capitol Construction |
|
|
June, 1919 |
|
Capitol Commission hires T.R. Kimball as architectural advisor |
|
|
December, 1919 |
|
Preliminary Competition identifies three Nebraska architects for Final Competition |
|
|
June, 1920 |
|
Judgement of Final Competition, Jury choses Bertram Grosvenor Goodhue |
|
|
November, 1920 |
|
Commission signs contract with Architect |
|
|
April 15, 1922 |
|
Groundbreaking for new Capitol by Governor Samuel R. McKelvie |
|
|
April, 1922 |
|
First contract awarded to W.J. Assenmacher Co. for the excavation of the site and laying of foundation. |
|
|
July, 1922 |
|
Contract awarded to J.H. Weise Co. for first phase superstructure construction (north and south sections of square base) |
|
|
November 11, 1922 |
|
Cornerstone laid with American Legion participating |
|
|
April 24, 1924 |
|
Death of architect Bertram Grosvenor Goodhue |
|
|
November, 1924 |
|
Contract signed with Bertram Grosvenor Goodhue Associates for continuance of archtiectural work |
|
|
December, 1924 |
|
State offices moved from old building to newly completed outer square of new building |
|
|
March 1925 |
|
Contracts awarded to J.H. Weise Co. for demolition of old Capitol |
|
|
April 1925 |
|
Contracts for second construction phase awarded to J.H. Weise Co. (east side, east, north and south arms of cross, and base of tower) |
|
|
February 1928 |
|
Contracts for third phase construction (tower) awarded to Peter Kiewit Sons Co. |
|
|
April 24, 1930 |
|
"The Sower" was raised to the top of the Capitol |
|
|
June 1930 |
|
Contracts awarded to W. J. Assenmacher Co. for the fourth phase of construction |
|
|
August, 1931 |
|
Contracts awarded for grounds lighting |
|
September, 1931 |
|
Contracts awarded for landscape excavating, grading and concrete work |
|
|
January, 1932 |
|
Contracts awarded for Furnishings including furniture and floor covering |
|
|
April, 1932 |
|
Contracts awarded for Lamp Posts |
|
|
May, 1932 |
|
Contracts awarded for sodding of the grounds |
|
|
February, 1934 |
|
Contracts awarded for
planting trees and shrubs on Capitol grounds |
|
|
|
List of Expenses: |
|
|
|
Architectural Expenses |
$452,074.68 |
|
|
Capitol Commission Expenses |
40,421.88 |
|
|
Inspection Expenses |
120,585.32 |
|
|
Miscellaneous Expense Items |
539,787.00 |
|
|
Furnishings and Decorations |
537,579.36 |
|
|
First Construction |
2,562,917.62 |
|
|
Wrecking Old Building |
49,642.81 |
|
|
Second Construction |
3,015,460.20 |
|
|
Third Construction |
1,487,309.74 |
|
|
Fourth Construction |
887,756.79 |
|
|
Landscaping |
131,093.46 |